This brownfield project expanded an operating gold CIL plant in Malaysia from 500 t/d to 800 t/d within its existing footprint. Xinhai Mining provided the process design, new grinding, classification and leaching equipment and installation guidance, while the client fabricated the feed conveyor and carried out the installation.
Existing-plant interface and layout: Mapped the retrofit boundary against the operating 500 t/d circuit and laid out new grinding, classification and leach equipment within the limited original footprint, issuing the feed-conveyor conditions for the client to fabricate the belt. Added new workshop bays so the expansion proceeded without stopping production.
One-stage grinding and two-stage classification: Installed an MQYg2445 long-cylinder overflow ball mill with an FLG2000 high-weir spiral classifier for first-stage classification and XCII 250×3 cyclones for the second stage. Cyclone underflow returns to the mill and overflow advances to de-shimming, producing a final pulp of 85% passing 200 mesh for leaching.
De-shimming and carbon retention screening: Reused the original DZS0918 linear screen as the new de-shimming screen to remove wood chips and debris, and replaced the original unit with a DZS1225 screen to handle the higher slag load. Extended the carbon screen from 1.5 m to 2.5 m to reduce gold-bearing carbon loss at the higher throughput.
CIL leach tank expansion and aeration: Added four SJ7.0×7.5 agitated leach tanks alongside the six existing units and installed a TRRE-250 high-pressure Roots blower to cover the insufficient air supply to tanks No.5 and No.6 and serve the new tanks and carbon transfer. Slurry, air and water lines were re-laid in DN200 welded steel pipe in place of the original DN150 sections.
Slurry transfer and buffering: The added tanks reduced the site head by 1.2 m, so gravity flow could no longer be maintained. A slurry pump was introduced to lift pulp to two existing red leach tanks, converted to tailings-pulp buffer tanks, and then to an SJ4.5×5.0 agitated tank, keeping transfer continuous across the new elevation profile.
Filter pressing and water recycling: Added an XMZ600/2000 chamber filter press with its feed pump and discharge conveyor, feeding from the buffer tanks and returning filtrate by gravity to the existing tank. New and return water is drawn from the high-level reservoir through PE piping, so no additional water pumps were required.
Construction drawing design began in August 2024 and was issued to the client in September 2024. The expanded line was commissioned in April 2025 and ran smoothly; by October 2025, the plant had reached an actual throughput of 850 t/d against its 800 t/d design basis, exceeding the target. The motors and reducers have held a zero-failure record since start-up, and the retrofit kept the original circuit producing throughout installation. This was the third plant project Xinhai delivered for the client, adding 300 t/d of capacity within the original footprint and reinforcing a long-running supply relationship.