A tailings storage facility was designed for a 3,000 t/d graphite concentrator in Tanzania, paired with the plant's process design and equipment supply. Xinhai Mining handled concentrator design, equipment and installation services, while the tailings dam design was subcontracted and the client placed equipment orders and managed construction.
Flake-protecting flowsheet: Designed the graphite circuit as crushing, coarse grinding, roughing, regrinding and cleaning, with stage grinding chosen to protect large flake graphite from over-grinding.
Tailings site selection: Selected a valley about 1.5 km northwest of the plant after site comparison, giving a total storage capacity of 7.786 million m³ and a 56 m maximum dam height for roughly 8.7 years of tailings deposition.
Wet deposition and transport: Specified wet tailings disposal, pumping thickener underflow at 40% mass concentration to the dam crest for distributed discharge through a pipeline routed along the valley terrain.
Dam structure: Designed a 26 m compacted rockfill starter dam with upstream raised sand dams built by the upstream method, plus two saddle dams, drainage layers and seepage collection.
Flood control and monitoring: Provided a well-and-tunnel spillway with three frame wells and about 1,287 m of tunnels, designed for 100-year early-stage and 200-year final-stage floods, with online and manual monitoring of displacement, phreatic line, beach length and water level.
Water return and closure: Returned tailings water to the plant's high-level tank and specified progressive reclamation with a 0.5 m soil cover at closure.
The tailings facility concept design was completed in May 2024, with the full scheme delivered in March 2025. Rated as a Class IV facility, the dam provides 7.786 million m³ of total storage and about 5.84 million m³ of usable capacity, serving an estimated 8.7 years of operation. Stability analyses returned safety factors above the specified minimum under normal, flood and special conditions, and the flake-protecting graphite flowsheet was developed from detailed condition testwork on ore grading 5.67% recoverable fixed carbon.