A 500 t/d gravity plant in Cameroon treats a 2–3 g/t gold ore using a client-specified circuit, which Xinhai Mining developed into a detailed design. Xinhai delivered engineering, equipment and installation, with the final flowsheet combining jigs, shaking tables, centrifugal concentrators and amalgamation to produce gold bullion.
Client-specified circuit: Converted the client's requested gravity route into a complete construction design covering feeding, grinding, gravity separation, smelting room, water supply, power, civil works and site roads.
Direct feeding and primary grinding: Fed the run-of-mine ore, which needed no crushing, through a belt feeder into a ball mill, then screened the discharge on a linear screen to remove oversize before concentration.
Coarse-gold recovery: Sent screened pulp to a jig for roughing and then through two stages of shaking tables, with table concentrate going to the smelting room for gold bullion.
Regrinding and classification: Pumped jig and table tailings to a second ball mill in closed circuit with cyclones, returning underflow to primary grinding and routing overflow through a thickener and a second cyclone group.
Fine-gold recovery: Treated the second cyclone overflow on a centrifugal concentrator and cleaned its concentrate on a shaking table for fine particle gold, again sending concentrate to smelting.
Amalgamation and refining: Passed table tailings to a gold amalgamator and forwarded the amalgam to the smelting room for retorting and casting into gold bullion.
The design contract took effect in April 2023 and the full construction drawing set was issued in June 2023. The plant was commissioned in June 2024 and reached its 500 t/d throughput. Built around a multi-stage gravity circuit, it recovers both coarse and fine particle gold into bullion and keeps the regrinding loop in closed circuit to limit gold loss in the tailings stream.