pending update
case

Mali 150 t/d Gold Mineral Processing Plant

The design scope of Mali 150tpd gold CIL beneficiation plant project included beneficiation (including water supply and drainage), electric power, civil engineering, general drawing, steel structure, etc.

If you want to know more information, like quotation, products, solutions, etc., please contact us online.

Xinhai Solution

  • 01

    It adopted screening and removing impurities-one stage wet grinding-CIL cyanide leaching-desorption electrolysis process. 

  • 02

    After sieving and removing impurities, the raw ore entered the ball mill for grinding. The grinding products were transported by the slurry pump to the hydrocyclone for classification, the hydrocyclone overflow entered the cyanide leaching process, and the hydrocyclone underflow returned to the ball mill. 

  • 03

    Tailings after cyanide leaching were transported to the tailings pond by the slurry pump; the gold-loaded carbon was stored in the storage tank and transported to the desorption electrolysis system.

Project Result

The project adopted a steel structure platform design, the equipment quality was reliable, the beneficiation index and economic benefits met the expectations, and the professional EPC+M+O service of Xinhai Mining had been strongly affirmed and recognized by the project customers.