Xinhai prepared the engineering design for a 100,000 t/a zircon sand tailings plant in Guangdong, covering preliminary design, safety design and construction drawings submitted for regulatory approval. The client retained equipment procurement and project implementation, with Xinhai's scope limited to the design package and the revisions requested during review.
Preliminary design: prepared the preliminary design for a plant treating zircon-bearing middle and tailings material, defining the circuit arrangement and the main plant configuration at 100,000 t/a.
Safety design: developed the safety-focused design chapter in line with the regulatory requirements for the project's approval path.
Construction drawing design: produced the construction drawings for the process, layout and supporting systems, providing the document set required for filing and review.
Regulatory filing support: compiled and submitted the documentation for planning and construction review, and revised the scheme when the authorities required further changes to the submitted plan.
Scheme revisions: updated the design in response to the review requests of 2024, keeping the drawing package consistent with the revised planning conditions.
The design package moved through preliminary design, safety design and construction drawings, and was submitted for regulatory filing. Planning approval was completed in December 2024, and the scheme revisions requested during review were incorporated into the resubmitted documents. At the June 2025 follow-up, the design was still in progress, with completion expected within the year.