Installation and Commission of Busolwa 12000TPD Gold CIL Plant Project

Busolwa 12000TPD Gold CIL Plant Project

2021-08-20 XinHai Views (1252)

If you want to know more information, like quotation, products, solutions, etc., please contact us online.

Precious video recording of Busolwa 12000TPD Gold CIL Plant. During the installation and commissioning process, Xinhai employees carry forward a work style of working hard to guarantee the high-quality accomplishment of the work in a short period. With the attitude of developing the rigorous Xinhai employees also got highly appreciated from the customer.

Xinhai Tanzania 1200tpd gold mineral processing project is located in Africa, thus has big differences from the domestic one in project management, construction technology, resource supply, and work coordination.

Mainly includes thickening, cyaniding, and desorption electrolysis parts. Main work of the installation and commissioning includes:

1.Install the equipment such as thickening, cyaniding, desorption electrolysis system;

2.Install the pipelines and operation platforms (exclude tailings pipelines of outdoors);

3.The electric power, water supply, and drainage. (exclude water supply from a water source);

This project applies all slime cyanidation to leach gold, the ore mainly sulfide ore and oxidized ore.

Civil construction mainly includes factory building and equipment foundation construction. after the foundation construction work of the thickening and leaching tank, the installation and construction of the pipeline and the electric instrument also should be finished.

Related Products

Latest Videos